HomeJobCosts

Full Bathroom Remodel Cost in 2026

A typical job is $20,000, in a range of $10,000 – $30,000. On its own that number means very little, so every figure on this page is drawn against the same $60,000 scale: against the other bathroom work you could be quoted for, and against the 20 metros where the job is priced.

Where this sits among bathroom work

national range, typical marked
Addition
$21,000 Full Remodel
$20,000 Kohler LuxStone Shower
$18,000 Re-Bath Remodel
$16,000 Jacuzzi Bath Remodel
$15,500 West Shore Home Bath Remodel
$15,000 Accessibility Remodel
$12,000 Walk-In Tub
$10,000 Bath Planet Bath Remodel
$10,000
$0$15k$30k$45k$60k

The same job, 20 metros

same $60,000 scale

Identical work, moved between labour markets. The whole range slides, so a dear metro's low can sit above a cheap metro's high. Colour runs with the metro's labour index, not with good or bad.

Chicago
$26,600 Seattle
$25,800 Minneapolis
$25,400 New York
$24,600 San Diego
$23,000 Portland
$23,000 Los Angeles
$22,800 Philadelphia
$22,400 Denver
$21,400 Las Vegas
$20,200 Phoenix
$19,800 Austin
$19,000 Houston
$18,600 Nashville
$18,600 Atlanta
$18,400 Charlotte
$18,400 Miami
$18,200 Dallas
$17,800 Tampa
$17,400 San Antonio
$17,000
$0$15k$30k$45k$60k

What the $20,000 is made of

Materials move with the market; labour moves with your metro. At 33% materials, only the smaller block is re-priced by the index — which is why a metro 33% above national does not raise this job by 33%.

Materials 33%
Labour 67%
$3,000 – $10,000 $6,000 – $18,000
$20,000
$10,000 $30,000
Full Bathroom Remodel — national range

Put your own numbers on the scale

Trade and project are fixed to this page; changing the metro re-applies its labour index to every figure above.

Cost Calculator

$24,600
$12,300$36,900
estimated total cost
Labor$7,380 – $22,140
Materials$3,690 – $12,300
Permit feeVaries by municipality
Total$12,300 – $36,900
23% above average in New York
Compare to Other Cities

To get exact pricing for your project, request written quotes from at least three licensed contractors in New York.

Based on aggregated data, a full bathroom remodel costs $10,000 to $30,000, with a mid-range project landing near $20,000. Materials account for $3,000 to $10,000 of that total and labor for $6,000 to $18,000. The two bands are compiled separately from published pricing, so they do not add up exactly to the total; the total is the figure to budget from. Typical on-site duration is 2 to 4 weeks, and the project is flagged as typically requiring a permit.

Those three tiers are not three grades of the same project. They are three different scopes:

The rest of this page takes the $20,000 apart line by line, and shows where each line goes at $10,000 and at $30,000.

The Line-Item Budget

This is the spine of the number. Every line below is a project this site prices individually, so a figure in the budget column can be checked against the standalone cost page for that line. The last two rows are the ones most budgets forget.

Line itemStandalone range$10,000 build$20,000 build$30,000 build
Plumbing rough-in$1,500–$5,000$1,500$3,000$4,000
Tub or shower unit$1,000–$8,000$1,500$3,500$5,500
Shower pan and waterproofing$500–$3,500$500$1,400$2,200
Shower valve and trim$200–$900$200$425$800
Shower door or enclosure$400–$3,000$400$1,000$2,000
Tile — floor and walls$1,500–$7,000$1,500$3,500$6,000
Vanity$500–$3,000$500$1,500$2,500
Sink and faucet$280–$1,400$280$650$1,200
Toilet$200–$700$200$400$600
Electrical, ventilation, drywall, paint, mirror, hardware—$2,420$2,625$3,200
Sum of the component lines$9,000–$28,000$9,000$18,000$28,000
Project total (compiled)$10,000–$30,000$10,000$20,000$30,000

Three things in that table are worth stopping on.

The component lines and the project total are two separate compilations. The lines are sized from this site’s own project data and come to $9,000 to $28,000; the project range, compiled from published full-remodel pricing, is $10,000 to $30,000. Neither is derived from the other, and where they differ the project total is the figure to budget from. The component lines show where the money goes, not an itemized invoice.

The component ranges do not stack. If every line above were bought at the top of its own standalone range, the fixtures alone would come to $32,500 — more than the entire $30,000 high-end project. A $30,000 bathroom is not a bathroom where every line is maxed; it is a bathroom where two or three lines are maxed and the rest are mid-grade. The $30,000 column above shows what that trade-off actually looks like: tile and rough-in near the top, toilet and sink well below it.

The unglamorous line is not small. Electrical, ventilation, drywall, paint, the mirror and the hardware carry no showroom appeal and run $2,420 to $3,200 across all three tiers — more than the toilet, sink and valve combined. It is the line that gets cut first and the line that produces the complaint about a beautiful bathroom with a fan that does not clear steam.

The labor share of a bathroom remodel is broken out separately, and the calculator above applies the same split to any project size and any of the 20 metros in the dataset.

What “Grade” Means Inside Each Line

The three columns are not three shopping trips at three price points. Each line has its own spread, and they are not the same shape.

Wide-spread lines — where grade genuinely changes the number. The tub or shower unit runs $1,000 to $8,000, an 8× spread: at the bottom is a stock alcove unit or a fiberglass surround, at the top a fully built shower with a bench, a niche and glass. Tile runs $1,500 to $7,000, a 4.7× spread that is mostly labor pattern rather than tile price. The vanity runs $500 to $3,000, a 6× spread between a stock unit off a shelf and a semi-custom cabinet with a stone top. The shower door runs $400 to $3,000, a 7.5× spread between a sliding aluminum-framed panel and heavy frameless glass templated to the finished opening. These four lines are where a bathroom’s budget is really decided — at the mid tier they account for $9,500 of a $20,000 project, nearly half of it.

Narrow-spread lines — where grade barely matters. The toilet runs $200 to $700 and the shower valve $200 to $900. Neither top figure exceeds $900, both spreads are small in absolute terms, and the money in each is mostly the plumber’s visit rather than the object. Buying an expensive toilet does not meaningfully move a $20,000 budget; buying a cheap one does not meaningfully save it.

Fixed lines — where grade does not exist. The plumbing rough-in and the electrical, ventilation and drywall line are priced by what the work is, not by what is chosen. A rough-in in the same locations costs what it costs. This is the half of the budget that is invisible in the finished room and that no amount of shopping reduces.

The practical consequence: a homeowner trying to hit $10,000 gets there by choosing narrow scope, not by choosing cheap fixtures. Downgrading every fixture in a $20,000 gut saves a few thousand. Not moving the plumbing and not building a tile shower saves considerably more.

Cost by Scope

“Bathroom remodel” describes four different projects with a factor-of-twenty spread between them. Scope, not finish level, is the first thing that decides the number.

ScopeWhat actually changesTypical rangeMid
Cosmetic refreshVanity, toilet, sink, faucet, regrout. No demolition beyond fixtures.$1,280–$7,100~$3,000
Pull-and-replace (small bath)Everything visible is replaced; walls, floor and drains stay.$3,000–$15,000$9,000
Full gut, same layoutDown to studs and subfloor. New rough-in in the same locations.$10,000–$30,000$20,000
Full gut plus layout changeDrains, vents and supply lines move.$11,500–$35,000$23,000

The cosmetic refresh range is simply the sum of its parts: a vanity ($500 to $3,000), a toilet ($200 to $700), a sink and faucet ($280 to $1,400) and shower regrouting ($300 to $2,000). Nothing is demolished, no permit is triggered, and the room is out of service for days rather than weeks. The low-cost bathroom remodel page works this tier in detail.

Pull-and-replace is where most homeowners think they are, and it is priced here at the small bathroom remodel range of $3,000 to $15,000. The distinction from a gut is not the fixture list — it is whether the walls come down. Leaving the walls up means leaving the waterproofing, the wiring and the framing exactly as they are, which is cheap and also means any problem behind them stays there.

The full gut is this page’s project: $10,000 to $30,000. The walls come off, the subfloor is exposed, and every system is visible and available. That is why the range is wide — the gut is also the discovery.

The layout change is the single most expensive decision available in a bathroom, and it is quantifiable. Moving a toilet, a tub or a shower drain pushes the plumbing rough-in line from the bottom of its $1,500 to $5,000 range toward the top: roughly $2,000 to $3,500 more than a same-location swap, on the rough-in alone. That figure excludes the knock-on costs, which are usually larger than the rough-in premium itself — the floor has to be opened to reach the drain, joists may need to be headed off or notched within code limits, the subfloor gets patched, and the tile has to be laid over a floor that is now partly new and partly old.

The cheapest bathroom remodel is the one where the toilet ends up where the toilet already was.

Remodel or Renovation — the Distinction That Sets the Price

The two words are used interchangeably in conversation and mean different things on an invoice. A renovation restores what is there: same layout, same fixture positions, new surfaces and new fixtures in the old places. A remodel changes what is there: walls, drains, vents or the footprint itself move. In the table above, the top two rows are renovations and the bottom two are remodels, and crossing that boundary is worth roughly $11,000 of median cost — a $9,000 pull-and-replace becomes a $20,000 gut.

The practical test is not how much is being spent — it is whether a plumber has to open a floor. Everything on the renovation side of that line is predictable, quotable and quick. Everything on the remodel side carries a discovery risk that no estimate can price in advance, because nobody has seen behind the wall yet.

Cost by Bathroom Type and Size

BathroomTypical areaRangeMid
Half bath / powder room15–25 sq ft$1,500–$12,000$4,500
Small full bath (5×8)35–45 sq ft$3,000–$15,000$9,000
Standard full bath60–100 sq ft$10,000–$30,000$20,000
Primary suite100+ sq ft$30,000 and up—

A half bath remodel ($1,500 to $12,000) has no bathing fixture at all, which deletes the four most expensive lines in the budget above — the tub or shower unit, the pan, the valve and the door, together $2,600 at the low tier and $10,500 at the high. What is left is a toilet, a sink, tile and paint. That is why a powder room with genuinely expensive finishes can still cost less than a plain full bath: it is not competing on the same line items.

The 5×8 small bathroom ($3,000 to $15,000) is the most common bathroom in American housing stock and the one most people mean by “the bathroom.” The fixture count is the same as a standard full bath — toilet, sink, tub-shower — so the savings come almost entirely from area-priced work: less tile, less drywall, less flooring. Labor barely moves, because the plumber still makes the same number of visits to hook up the same number of fixtures. This is the clearest demonstration on the site that a bathroom is priced by fixture count, not by square footage; the per-square-foot page shows how badly a rate-per-square-foot estimate misprices small bathrooms as a result.

A primary suite is not a bigger version of a full bath — it is a full bath with a second bathing fixture. The standard configuration is a tub and a separate walk-in shower, and a walk-in shower is a $4,000 to $20,000 project in its own right ($9,000 mid). Added alongside a tub, a double vanity and a larger tiled floor, it puts a primary suite above the $30,000 top of the full-bath range as a matter of arithmetic, not luxury.

Materials vs Labor — Why a Bathroom Is the Most Labor-Heavy Room in a House

ComponentLowMidHighShare of the $20,000 mid project
Materials (fixtures, tile, vanity, trim)$3,000$6,000$10,00030%
Labor (demo, plumbing, electrical, tile, finish)$6,000$12,000$18,00060%
Project total (compiled)$10,000$20,000$30,000

Labor is twice the materials bill. In a kitchen the ratio is closer to even, because a kitchen’s cost is loaded into cabinetry and appliances — objects that are bought, not built. A bathroom has almost no expensive objects in it. A $400 toilet, a $650 sink, a $1,500 vanity and $3,500 of tile is not a lot of money in materials. What it costs is the sequencing.

A full bathroom remodel puts four to six trades into 40 to 100 square feet, and they cannot work simultaneously or out of order:

  1. Demolition strips the room to studs and subfloor.
  2. Plumbing rough-in — 2 to 4 days on its own — sets the drain, vent and supply lines. It cannot start until demolition ends and it must pass inspection before anything covers it.
  3. Electrical runs circuits, GFCI protection, lighting and the exhaust fan. It shares open walls with the plumber and competes for the same cavities.
  4. Waterproofing and backer board close the walls. From this point every mistake underneath is permanent.
  5. Tile — 3 to 7 days — is the longest single trade in the room and the one that cannot be rushed, because thinset and grout cure on their own schedule.
  6. Finish and fixture set hangs the vanity, sets the toilet, installs the shower door and trims out the valve.

Each of those is a separate mobilization: a truck, a crew, a minimum charge, and a day that is partly travel. Six mobilizations across a room the size of a parking space is what a bathroom’s labor line is actually buying. It also explains why the small bath and the standard bath are so much closer in labor than in area — the crew count does not shrink with the room.

The 2-to-4-week timeline is the same fact expressed in days rather than dollars.

The $2,420-to-$3,200 Line Nobody Shops For

Electrical, ventilation, drywall, paint, the mirror and the hardware are the one budget line with no showroom, no comparison shopping and no emotional pull — and across all three tiers it costs more than the toilet, the sink and the valve put together.

What is inside it is not optional. A bathroom needs GFCI protection on its receptacles and a dedicated circuit for anything drawing real load. It needs an exhaust fan sized to the room and ducted to the outside rather than into the attic, because a fan that vents into insulation is the most efficient mold-generating device available. Priced on its own rather than inside the remodel, bathroom exhaust fan installation runs $200 to $1,200 and is 70 percent labor at every point in that range — which is why the fan is the cheapest item in this line to specify correctly while the ceiling is still open. It needs moisture-rated wall board on the wet walls and cement or foam backer behind tile. It needs a vapor-tolerant paint. And once the walls are open, adding a circuit or moving a light costs almost nothing, while adding one after the tile is up means opening the tile.

This is the line where a $10,000 budget and a $30,000 budget differ least in absolute terms — $2,420 against $3,200, a swing of under $800 — because the code-driven minimum is close to the practical maximum. A cheap bathroom does not get cheap wiring; it gets a cheaper vanity.

Accessibility and Aging-in-Place

An accessibility-focused bathroom is priced as its own project in this dataset rather than as an upgrade to a standard one: $5,500 to $20,000, with a mid near $12,000, over 1 to 3 weeks, typically requiring a permit. That range sits below the standard full remodel at the top end and above it at the bottom, which reflects what the work actually is — some of it is cheap hardware, some of it is structural.

The cheap end is grab bars, a comfort-height toilet, a handheld shower on a slide bar, lever handles and better lighting, and it can be done without demolition. The expensive end is a curbless roll-in shower, which is not a fixture change at all — it is a floor change. Getting a shower floor flush with the bathroom floor means dropping the shower pan below the surrounding subfloor, which means cutting into or furring around the joists, relocating the drain and rebuilding the framing. That is why it prices closer to a layout change than to a shower swap.

The middle of the range is usually a walk-in tub — $4,000 to $22,000 on its own, mid $10,000, the widest range of any single fixture on this site. The spread is real: a basic soaking model with a low door threshold sits near the bottom, while hydrotherapy jets, a heated seat, a fast-drain system and the electrical circuit they require sit at the top. A walk-in tub also occupies the same footprint as a standard tub, which is the reason it is the most common accessibility retrofit that does not become a full remodel.

City-Adjusted Cost

Materials price broadly nationally — a toilet, a vanity and a box of porcelain tile cost about the same in Houston as in Seattle. Labor does not. Because labor is 60 percent of this project and materials only 30, the city factor moves a bathroom remodel more than it moves almost anything else the site prices.

The table below holds materials flat at the mid-range $6,000 and scales only the $12,000 labor half by each metro’s labor adjustment factor.

City Labor Adjustment Factor Materials + Labor (mid)Labor Portion Only vs. National
Chicago, IL 1.33 $21,960$15,960 +33%
New York, NY 1.23 $20,760$14,760 +23%
Seattle, WA 1.29 $21,480$15,480 +29%
Houston, TX 0.93 $17,160$11,160 −7%
San Antonio, TX 0.85 $16,200$10,200 −15%

Labor adjustment factors are derived from BLS Occupational Employment and Wage Statistics (May 2025): the median ratio of local to national hourly wages across the trades that do this work. How this is calculated.

Chicago carries the highest factor in the dataset at 1.33 — higher than New York at 1.23 — which surprises people who expect the ranking to follow cost of living. It does not. Trade labor is priced by union density, licensing regime and local contractor supply, and Chicago’s plumbing and tile trades are among the most expensive in the country. San Antonio sits at the other end at 0.85. The same $20,000 bathroom, same fixtures, same tile, is a materially different project in the two markets, and essentially all of the difference lands in the labor column.

What Blows the Budget

Six things account for most of the gap between the quote and the final invoice.

1. Moving the plumbing — $2,000 to $3,500 on the rough-in, plus knock-on. Covered above. It is the only line here that is a decision rather than a discovery, which makes it the only one that is fully controllable.

2. What the demolition finds — the largest unbounded risk. A bathroom is the wettest room in the house, and a gut is the first honest look behind its walls in decades. Rotted subfloor, a joist soft under the toilet flange, failed pan liner, and mold behind tile that was grouted over rather than waterproofed are common findings, not rare ones. Water-damaged framing and subfloor are priced separately — see water-damaged floor repair and subfloor replacement — and none of it is in the $10,000 to $30,000 range, because none of it is part of a remodel. It is a repair the remodel exposed. The EPA publishes guidance on mold in buildings, and remediation scope is determined by the affected area, not by the remodel budget. Homes built before 1978 add a further variable: disturbed lead paint and old asbestos-backed floor tile both carry handling requirements that change who can do the demolition and what it costs.

3. Custom tile work. The tile line runs $1,500 to $7,000, and the spread inside it is labor, not tile. A 12×24 porcelain field on a flat wall is fast. A herringbone or hex mosaic, a curbless entry, a niche with mitred edges, a full-height slab surround, or a pattern that has to be laid out symmetrically around a window doubles the hours on the same square footage. Tile shower installation is the sub-project where this shows up most sharply, and acrylic versus tile is the decision that sets it.

4. Lead times forcing a second mobilization. A vanity on a 10-week lead time, a valve trim on backorder, or a shower glass panel that has to be templated after the tile is set will pull a trade back for a second visit. The materials cost the same; the labor does not. This is the mechanism behind most “the remodel took twice as long as quoted” outcomes, and it is why the tile and finish trades are the ones that most often return.

5. Change orders. Every change after demolition is priced without competition, because the crew is already in the room and no other bid exists. Upgrading the tile after the layout has been set, adding a niche, moving a light — each is small, and they compound.

6. Scope creep into the fixture set. A bathtub replacement at $1,500 becomes a $9,000 walk-in shower; a standard tub becomes a $10,000 walk-in tub; a shower alcove becomes a tub-to-shower conversion. Each is defensible on its own. The tub versus shower cost comparison exists because this is the decision that most often moves a $20,000 project to $25,000 after work has started.

Where the Budget Comes Back Down

The same table that explains the overrun explains the savings, because every lever is a line in it. Ranked by how much they move the number:

Bidding is where the last of it is found. Because 60 percent of the cost is labor and labor is quoted rather than listed, two bids on an identical bathroom can differ by thousands without either being wrong — they differ on how many days each trade is allowed. Bids that itemize the rough-in, tile, and fixture-set lines separately can be compared; a single lump-sum figure cannot.

Permits, Inspections and Timeline

A full bathroom remodel is flagged in this dataset as typically requiring a permit, as is the bathroom plumbing rough-in inside it. The trigger is systems work, not finishes: new or relocated drain and vent lines, new circuits, and GFCI protection. A fixture-for-fixture swap in the same location frequently does not require one; opening a floor to move a drain almost always does. Requirements are set by the local jurisdiction and vary; most are written against a version of the International Residential Code, which is what the inspector is reading from.

Inspections are the reason calendar time exceeds work time. The rough-in inspection happens with the walls open, before insulation or backer board, and nothing can cover the pipes until it passes. A day of waiting between the plumber finishing and the tile setter starting is normal, not a delay.

PhaseTypical durationNotes
Demolition1–2 daysRoom out of service from here on
Plumbing rough-in2–4 daysPermit and rough-in inspection
Electrical rough-in1–2 daysRuns alongside plumbing where walls allow
Waterproofing and backer1–2 daysClose-up follows inspection
Tile3–7 daysIncludes cure time between set and grout
Vanity, fixtures, finish2–4 daysGlass door often templated after tile
Full remodel, on site2–4 weeksLead times can extend calendar time further

DIY vs Professional

The DIY question in a bathroom is not one question, because the room contains six trades and they are not equally accessible to an owner. Demolition, painting, and setting a vanity, toilet and sink are the accessible ones. Waterproofing a shower, soldering or crimping supply lines, cutting into a drain stack and running a GFCI circuit are the ones where a mistake is not visible until it has done damage — a pan liner that leaks does so behind finished tile, into a subfloor, for months.

The full arithmetic — which lines can realistically be self-performed, what the tools and rentals actually cost, and how much of the $6,000 to $18,000 labor line a homeowner can genuinely capture — is worked through on the DIY bathroom remodel cost page rather than duplicated here. The short version from the data: the labor is 60 percent of the project, but it is not 60 percent available. The most commonly self-performed lines — demo, paint, and the toilet, sink and vanity set — sit near the bottom of the labor stack in both hours and dollars.

Every line in the budget at the top of this page has its own priced sub-project. The bathing fixture is the largest and the most variable: a shower remodel spans $1,500 to $15,000 on its own, shower installation $1,000 to $8,000, and the shower pan under it $500 to $3,500. Surfaces follow: bathroom tile at $1,500 to $7,000, with general tile installation pricing covering the floor. For a bathroom floor that is not tile, waterproof flooring options is the relevant comparison.

The smaller lines add up faster than expected: a bathroom sink at $280 to $1,400, a toilet at $200 to $700, a shower valve at $200 to $900 and a vanity at $500 to $3,000 come to $1,180 at the bottom and $6,000 at the top — a $4,820 swing across four items nobody thinks of as the expensive part.

Whether the money comes back at sale is a separate question from what it costs, and the two are often conflated. The National Association of Realtors publishes a Remodeling Impact Report covering cost recovery on interior projects; what a bathroom remodel does to home value works it against the ranges on this page rather than restating a national average.

Two structural points sit underneath any recovery figure. First, cost recovery is measured against what was spent, so the same finished bathroom recovers a very different percentage at $12,000 than at $28,000 — the numerator is the market’s opinion of the room and the denominator is the invoice. Second, the half of the budget that does not show — rough-in, waterproofing, wiring, ventilation — recovers nothing visible at all, but its absence is what a buyer’s inspector finds. A bathroom is one of the few rooms where the invisible work is what protects the value of the visible work, and where deferring it does not save money so much as move it into a future repair.

The bathroom remodeling cost overview covers every sub-project in the trade, the calculator applies a city factor to any of them, and the methodology page sets out how the national ranges are compiled and how the labor adjustment is measured.

Last updated: October 2026. All figures reflect aggregated national cost data and are not a quote for a specific bathroom. Actual pricing depends on scope, fixture selection, existing conditions and local market. See the methodology page for how figures are calculated and sourced.

Questions

How much does a full bathroom remodel cost?
Based on aggregated data, a full bathroom remodel costs $10,000 to $30,000, with a mid-range project landing near $20,000. Within that total, materials account for $3,000 to $10,000 and labor for $6,000 to $18,000. The two bands are compiled separately from published pricing, so they do not add up exactly to the total, and the total is the figure to budget from.
What does a $20,000 bathroom remodel actually get you?
At the $20,000 mid-range figure, aggregated data supports a full gut in the existing footprint: a $3,000 plumbing rough-in, a $3,500 tub or shower unit, a $1,400 shower pan, a $425 valve, a $1,000 shower door, $3,500 of floor and wall tile, a $1,500 vanity, a $650 sink and faucet, a $400 toilet and roughly $2,625 of electrical, ventilation, drywall and paint. Those lines come to about $18,000; the rest of the $20,000 total is not itemized in this dataset.
How much does it cost to gut a bathroom?
Gutting — stripping the room to studs and subfloor — is not priced as a standalone line in this dataset; the demolition labor sits inside the $6,000 to $18,000 labor band. A gut is what turns a pull-and-replace into a full remodel, and it is the point at which hidden rot, failed waterproofing and outdated wiring become visible and billable.
Why is labor 60 percent of a bathroom remodel?
Based on aggregated data, labor runs $6,000 to $18,000 against $3,000 to $10,000 of materials — about 60 percent of a mid-range $20,000 project versus 30 percent for materials. A bathroom concentrates four to six trades into roughly 40 to 100 square feet: demolition, plumbing, electrical, waterproofing, tile and finish carpentry, each needing its own visit in its own sequence. The square footage is small; the trade count is not.
How much does moving the plumbing add to a bathroom remodel?
Relocating a toilet, tub or drain moves the plumbing rough-in line from the bottom of its $1,500 to $5,000 range toward the top. Against a same-location swap, that is roughly $2,000 to $3,500 in additional cost on the rough-in alone, before the added demolition, floor patching and re-tiling that opening the floor requires.
Does a full bathroom remodel need a permit?
In this dataset a full bathroom remodel is flagged as typically requiring a permit, as is the bathroom plumbing rough-in inside it. Permits attach to the systems work — new drain lines, vent stacks, circuits and GFCI protection — not to the finishes. A fixture-for-fixture swap in the same location often does not trigger one; moving a drain almost always does. Requirements are set locally and vary by jurisdiction.
How long does a full bathroom remodel take?
Aggregated data puts a full bathroom remodel at 2 to 4 weeks of on-site work. The plumbing rough-in alone accounts for 2 to 4 days, tile 3 to 7 days, and the bathroom is unusable for most of the run. Calendar time is usually longer than work time, because inspections and material lead times create gaps between trades.
Does a full bathroom remodel cost more in some cities?
Yes, and the difference is in the labor half. Materials price broadly nationally, so applying city labor adjustment factors to the mid-range split of $6,000 in materials plus $12,000 in labor produces a spread of several thousand dollars across metros. Chicago carries the highest factor in the dataset at 1.33 and San Antonio the lowest at 0.85.

How the scale is built

Base ranges

Metro adjustment

Labor adjustment factors are measured from BLS metropolitan wage data: the median ratio of local to national hourly wages across the ten trades this site prices.

Drawing rules

Every chart on a page shares one axis unless its caption says otherwise. Bars are drawn from zero and are never truncated. Full method →

Last updated: October 2026

Estimates, not quotes. These cost estimates are based on aggregated data from public sources. Actual costs vary by project scope, contractor, and local conditions. Always obtain multiple written quotes from licensed professionals. This site sells nothing, lists no contractors and takes no payment for placement. Methodology →

Cost data last updated: October 2026

Related bathroom costs